PacifiCorp-C2-178
199 MW storage in Crook, OR · In queue since May 2022 · Proposed COD December 2028
199 MW
Capacity
1
Components
Battery
4 years
In Queue
—
IA Status
COD target: 2028
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PacifiCorp-C2-178 is a proposed 199 MW battery storage project located in Crook County, Oregon. The project, developed by PacifiCorp, is currently active in the PacifiCorp interconnection queue as of May 15, 2022, with a proposed commercial operation date of December 31, 2028. The point of interconnection is the Corral substation.
The project consists entirely of battery storage, with a total capacity of 199 MW. There is no information available regarding an interconnection agreement or news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Corral substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.