PacifiCorp-C2-179
40 MW generation in Millard, UT · In queue since May 2022 · Proposed COD December 2029
40 MW
Capacity
1
Components
Geothermal
4 years
In Queue
Suspended
IA Status
COD target: 2029
Total Duration
7y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
PacifiCorp-C2-179 is a proposed 40 MW geothermal generation project located in Millard County, Utah. The project, under development by FEC Development LLC, is interconnected to the PacifiCorp system at the Black Rock substation.
The project is listed in the PacifiCorp interconnection queue as entry C2-179, with a queue entry date of May 15, 2022, and a proposed commercial operation date of December 31, 2029. Its interconnection agreement status is currently listed as Suspended.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
FEC Development LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Black Rock substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-179