PacifiCorp-C2-203
400 MW hybrid in Klamath, OR · In queue since May 2022 · Proposed COD December 2025
400 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
3y 7m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PacifiCorp-C2-203 is a proposed 400 MW hybrid solar and battery project located in Klamath County, Oregon. The development project consists of 400 MW of solar generation. It is listed in the PacifiCorp interconnection queue as of May 15, 2022, with a proposed commercial operation date of December 31, 2025.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Klamath CoGen-Meridian transmission line.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Klamath CoGen-Meridian transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.