PacifiCorp-C2-205
150 MW hybrid in Cache, UT · In queue since May 2022 · Proposed COD October 2026
150 MW
Capacity
1
Components
Solar
4 years
In Queue
—
IA Status
COD target: 2026
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
PacifiCorp-C2-205 is a proposed 150 MW hybrid solar and battery project located in Cache County, Utah. The project consists of 150 MW of solar generation capacity. It is listed as active in the PacifiCorp interconnection queue, with an entry date of May 15, 2022, and a proposed commercial operation date of October 31, 2026. The point of interconnection is the Bridgerland-Cache transmission line.
The development project is located in the Western region and is being proposed by PacifiCorp.
Generated from interconnection queue and public data sources
State
UT
County
Cache
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Bridgerland-Cache transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-205