PacifiCorp-C2-208
320 MW hybrid in Harney, OR · In queue since May 2022 · Proposed COD December 2027
320 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
PacifiCorp-C2-208 is a proposed 320 MW hybrid solar and battery project located in Harney County, Oregon. The development project, consisting of 320 MW of solar capacity, is in the PacifiCorp interconnection queue, with an entry date of May 15, 2022. The proposed commercial operation date is December 1, 2027.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Burns-Summer Lake transmission line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
OR
County
Harney
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Burns-Summer Lake transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-208