PacifiCorp-C2-209
20 MW storage in Uintah, UT · In queue since May 2022 · Proposed COD October 2025
20 MW
Capacity
1
Components
Battery
4 years
In Queue
IA Executed
IA Status
COD target: 2025
Total Duration
3y 5m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2025-10-01
PacifiCorp-C2-209 is a proposed 20 MW battery storage project located in Uintah County, Utah. The project, under development by Revolve Vernal BESS, LLC, consists of a 20 MW battery energy storage system. It is interconnected to the PacifiCorp grid at the Ashley substation.
The project is currently active in the PacifiCorp interconnection queue, with an interconnection request date of May 15, 2022, and a proposed commercial operation date of October 1, 2025. The interconnection agreement for the project has been executed.
Generated from interconnection queue and public data sources
State
UT
County
Uintah
Grid Region
Mountain West
Market
—
Developer
Revolve Vernal BESS, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Ashley substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-209