PacifiCorp-C2-210
80 MW hybrid in Harney, OR · In queue since May 2022 · Proposed COD August 2026
80 MW
Capacity
1
Components
Solar
4 years
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-08-01
PacifiCorp-C2-210 is a proposed 80 MW hybrid solar and battery project located in Harney County, Oregon. The development project consists of 80 MW of solar generation capacity. It is listed as active in the PacifiCorp interconnection queue, with a queue entry date of May 15, 2022.
The proposed commercial operation date for PacifiCorp-C2-210 is August 1, 2026. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Burns-Summer Lake transmission line.
Generated from interconnection queue and public data sources
State
OR
County
Harney
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Burns-Summer Lake transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.