PacifiCorp-C2-39
300 MW hybrid in Iron, UT · In queue since April 2022 · Proposed COD December 2025
300 MW
Capacity
1
Components
Solar
4y 1m
In Queue
—
IA Status
COD target: 2025
Total Duration
3y 8m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PacifiCorp-C2-39 is a proposed 300 MW hybrid solar and battery project located in Iron County, Utah. The development project consists of 300 MW of solar generation capacity. It is listed in the PacifiCorp interconnection queue as of April 28, 2022, with a proposed commercial operation date of December 31, 2025. The point of interconnection is the Three Peaks substation.
The project is currently listed as active in the interconnection queue. Recent news coverage has discussed PacifiCorp's renewable energy development plans in Utah, including projects of this type.
Generated from interconnection queue and public data sources
State
UT
County
Iron
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Three Peaks substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.