PacifiCorp-C2-82
300 MW hybrid in Bannock, ID · In queue since May 2022 · Proposed COD December 2027
300 MW
Capacity
1
Components
Solar
4 years
In Queue
IA Executed
IA Status
COD target: 2027
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2027-12-31
PacifiCorp-C2-82 is a proposed 300 MW hybrid solar and battery project located in Bannock County, Idaho. The development project, sponsored by BRP Garnet 1, LLC, consists of 300 MW of solar generation. It is listed in the PacifiCorp interconnection queue as entry C2-82, with a queue entry date of May 12, 2022, and a proposed commercial operation date of December 31, 2027. The interconnection point is the Populus substation, and the project's Interconnection Agreement (IA) has been executed.
The project is currently listed as active in the interconnection queue. Recent news coverage has discussed the project's progress and potential impact on the region's energy infrastructure.
Generated from interconnection queue and public data sources
State
ID
County
Bannock
Grid Region
Mountain West
Market
—
Developer
BRP Garnet 1, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Populus substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C2-82