PacifiCorp-C3-021
100 MW generation in Walla Walla, WA · In queue since May 2023 · Proposed COD December 2026
100 MW
Capacity
1
Components
Wind
3 years
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PacifiCorp-C3-021 is a proposed 100 MW wind generation project located in Walla Walla County, Washington. The project, developed by PacifiCorp, is listed as active in the PacifiCorp interconnection queue, with an entry date of May 1, 2023. The proposed commercial operation date is December 31, 2026. The point of interconnection is the Wallula substation.
The project consists of 100 MW of wind generation capacity. There is no information available regarding an interconnection agreement or news coverage.
Generated from interconnection queue and public data sources
State
WA
County
Walla Walla
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Wallula substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.