PacifiCorp-C3-022
300 MW hybrid in Sweetwater, WY · In queue since May 2023 · Proposed COD December 2027
300 MW
Capacity
1
Components
Wind
3 years
In Queue
—
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PacifiCorp-C3-022 is a proposed 300 MW hybrid wind and battery project located in Sweetwater County, Wyoming. The project consists of 300 MW of wind generation capacity. It is listed as active in the PacifiCorp interconnection queue, with an entry date of May 2, 2023, and a proposed commercial operation date of December 31, 2027. The point of interconnection is the Anticline substation.
The development project is located in the West region. The listed utility and entity are both PacifiCorp. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
WY
County
Sweetwater
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Anticline substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.