PacifiCorp-C3-036
500 MW hybrid in Millard, UT · In queue since May 2023 · Proposed COD January 2027
500 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-07
PacifiCorp-C3-036 is a proposed 500 MW hybrid solar and battery project located in Millard County, Utah. The development project consists of 500 MW of solar generation. It is listed in the PacifiCorp interconnection queue as of May 8, 2023, with a proposed commercial operation date of January 7, 2027. The point of interconnection is the Pavant substation.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Pavant substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.