PacifiCorp-C3-038
199 MW hybrid in Converse, WY · In queue since May 2023 · Proposed COD July 2027
199 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2027
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
PacifiCorp-C3-038 is a proposed 199 MW solar and battery hybrid project located in Converse County, Wyoming. The development project consists of 199 MW of solar generation capacity.
The project is listed in the PacifiCorp interconnection queue with an entry date of May 8, 2023. Its proposed commercial operation date is July 1, 2027, and it intends to interconnect at the Casper - Latigo transmission line. The project's interconnection status is listed as active.
Generated from interconnection queue and public data sources
State
WY
County
Converse
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Casper - Latigo transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-038