PacifiCorp-C3-040
150 MW hybrid in Emery, UT · In queue since May 2023 · Proposed COD July 2028
150 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-31
PacifiCorp-C3-040 is a proposed 150 MW hybrid solar and battery project located in Emery County, Utah. The development project consists of 150 MW of solar generation capacity. It is listed in the PacifiCorp interconnection queue as of May 8, 2023, with a proposed commercial operation date of July 31, 2028. The point of interconnection is the Emery - Sigurd #2 transmission line.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Emery - Sigurd #2 transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-040