Project PacifiCorp-C3-053 — Project Summary

Queue ID
PacifiCorp-C3-053
Capacity
300 MW
Technology
Gas
Status
active
Location
Utah, UT
Region
West
Developer
IA Status

PacifiCorp-C3-053

PacifiCorp-C3-053BetaActiveGasPacifiCorpLBNL

300 MW generation in Utah, UT · In queue since May 2023 · Proposed COD December 2025

300 MW

Capacity

1

Components

Gas

3 years

In Queue

IA Status

COD target: 2025

Interconnection

Total Duration

2y 7m

Schedule

4 months past proposed COD

Pre-Study0%
Queue EntryMay 10, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

About

PacifiCorp-C3-053 is a proposed 300 MW natural gas generation project located in Utah County, Utah. The project, sponsored by PacifiCorp, entered the PacifiCorp interconnection queue on May 10, 2023, with a proposed commercial operation date of December 31, 2025. The point of interconnection is the Mercer substation.

The project consists of 300 MW of natural gas-fired generation capacity. As of the latest data, the project is listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

UT

County

Utah

Grid Region

Mountain West

Market

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Mercer substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PacifiCorp-C3-053