PacifiCorp-C3-061
120 MW hybrid in San Juan, UT · In queue since May 2023 · Proposed COD December 2026
120 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
PacifiCorp-C3-061 is a proposed 120 MW solar and battery hybrid project located in San Juan County, Utah. The development project consists of 120 MW of solar generation. It is listed in the PacifiCorp interconnection queue, with an entry date of May 11, 2023, and a proposed commercial operation date of December 1, 2026. The point of interconnection is the Pinto substation.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
San Juan
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Pinto substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-061