PacifiCorp-C3-072
10 MW hybrid in Box Elder, UT · In queue since May 2023 · Proposed COD December 2024
10 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2024
Total Duration
1y 7m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PacifiCorp-C3-072 is a proposed 10 MW hybrid solar and battery project located in Box Elder County, Utah. The development project, consisting of 10 MW of solar generation, is in the PacifiCorp interconnection queue with an entry date of May 11, 2023. The proposed commercial operation date is December 31, 2024.
The project is interconnected at the Lampo substation. As of the latest data, the project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Box Elder
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Lampo substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-072