PacifiCorp-C3-074
2 MW generation in Millard, UT · In queue since May 2023 · Proposed COD December 2023
2 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2023
Total Duration
7 months
Schedule
28 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-12-31
PacifiCorp-C3-074 is a proposed 2 MW solar generation project located in Millard County, Utah. The project is listed in the PacifiCorp interconnection queue as entry C3-074, with a queue entry date of May 11, 2023. The proposed commercial operation date is December 31, 2023. The point of interconnection is the Clear Lake substation.
The development project is currently listed as active in the interconnection queue. The project is being developed by PacifiCorp.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Clear Lake substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.