PacifiCorp-C3-097
19.9 MW generation in Jefferson, OR · In queue since May 2023 · Proposed COD December 2028
19.9 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PacifiCorp-C3-097 is a proposed solar generation project located in Jefferson County, Oregon. The development project, with a total capacity of 19.9 MW, is being developed by PacifiCorp. It consists of a single 19.9 MW solar component.
The project is currently active in the PacifiCorp interconnection queue, with an entry date of May 12, 2023. The proposed commercial operation date is December 31, 2028, and the point of interconnection is the Warm Springs substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Warm Springs substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-097