PacifiCorp-C3-132
199 MW hybrid in Millard, UT · In queue since May 2023 · Proposed COD December 2027
199 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
PacifiCorp-C3-132 is a proposed 199 MW hybrid solar and battery project located in Millard County, Utah. The development project consists of 199 MW of solar generation capacity. It is listed in the PacifiCorp interconnection queue as of May 15, 2023, with a proposed commercial operation date of December 1, 2027. The point of interconnection is the Pavant - Sigurd transmission line.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Pavant - Sigurd transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-132