PacifiCorp-C3-154
199 MW generation in Bingham, ID · In queue since May 2023 · Proposed COD December 2028
199 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PacifiCorp is proposing a 199 MW solar generation project in Bingham County, Idaho, identified as PacifiCorp-C3-154. The project is located in the West region and consists of 199 MW of solar capacity. It is currently listed as active in the PacifiCorp interconnection queue, with an entry date of May 15, 2023, and a proposed commercial operation date of December 31, 2028. The point of interconnection is the Antelope - Goshen transmission line.
Generated from interconnection queue and public data sources
State
ID
County
Bingham
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Antelope - Goshen transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-154