PacifiCorp-C3-162
20 MW hybrid in Emery, UT · In queue since May 2023 · Proposed COD September 2026
20 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
PacifiCorp-C3-162 is a proposed 20 MW hybrid solar and battery project located in Emery County, Utah. The development project consists of 20 MW of solar generation capacity. It is listed in the PacifiCorp interconnection queue as entry C3-162, with a queue entry date of May 15, 2023, and a proposed commercial operation date of September 30, 2026. The point of interconnection is the Columbia substation.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Columbia substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-162