PacifiCorp-C3-169
150 MW storage in Siskiyou, CA · In queue since May 2023 · Proposed COD March 2026
150 MW
Capacity
1
Components
Battery
3 years
In Queue
—
IA Status
COD target: 2026
Total Duration
2y 10m
Schedule
1 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-03-30
PacifiCorp-C3-169 is a proposed 150 MW battery storage project located in Siskiyou County, California. The project is listed in the PacifiCorp interconnection queue with an entry date of May 15, 2023, and a proposed commercial operation date of March 30, 2026. The point of interconnection is the Copco #2 substation.
The development project consists solely of battery storage, with a total capacity of 150 MW. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
Siskiyou
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Copco #2 substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-169