PacifiCorp-C3-172
100 MW storage in Jefferson, ID · In queue since May 2023 · Proposed COD June 2027
100 MW
Capacity
1
Components
Battery
3 years
In Queue
—
IA Status
COD target: 2027
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
PacifiCorp-C3-172 is a proposed 100 MW battery storage project located in Jefferson County, Idaho. The project, under development by PacifiCorp, consists of a 100 MW battery energy storage system (BESS). It is interconnected to the PacifiCorp system at the Jefferson substation.
The project is currently active in the PacifiCorp interconnection queue, with an entry date of May 15, 2023. The proposed commercial operation date is June 30, 2027. The project has appeared in recent news coverage regarding PacifiCorp's development plans.
Generated from interconnection queue and public data sources
State
ID
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Jefferson substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C3-172