PacifiCorp-C4-001
3.6 MW generation in Beaver, UT · In queue since April 2024 · Proposed COD December 2025
3.6 MW
Capacity
1
Components
Geothermal
2y 1m
In Queue
—
IA Status
COD target: 2025
Total Duration
1y 8m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PacifiCorp-C4-001 is a proposed 3.6 MW geothermal generation project located in Beaver County, Utah. The project, developed by PacifiCorp, entered the PacifiCorp interconnection queue on April 4, 2024, with a proposed commercial operation date of December 31, 2025. The point of interconnection is Circuit SCM11 out of the School Mine substation.
The project is currently listed as active in the interconnection queue. No information is available regarding an interconnection agreement or news coverage.
Generated from interconnection queue and public data sources
State
UT
County
Beaver
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Circuit SCM11 out of School Mine substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-001