PacifiCorp-C4-002
20 MW generation in Millard, UT · In queue since April 2024
20 MW
Capacity
1
Components
Geothermal
2y 1m
In Queue
—
IA Status
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
PacifiCorp-C4-002 is a proposed 20 MW geothermal generation project located in Millard County, Utah. The project, developed by PacifiCorp, is listed in the PacifiCorp interconnection queue as of April 12, 2024. The point of interconnection is the Sigurd - West Cedar transmission line.
The project is currently listed as active in the interconnection queue. No proposed commercial operation date or interconnection agreement status is available.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Sigurd - West Cedar transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-002