PacifiCorp-C4-003
20 MW generation in Sevier, UT · In queue since April 2024
20 MW
Capacity
1
Components
Geothermal
2y 1m
In Queue
—
IA Status
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
PacifiCorp-C4-003 is a proposed 20 MW geothermal generation project located in Sevier County, Utah. The project is listed in the PacifiCorp interconnection queue as of April 12, 2024, and is currently active. The point of interconnection is the Sevier substation.
The development project is sponsored by PacifiCorp. It is located in the Western region of the United States.
Generated from interconnection queue and public data sources
State
UT
County
Sevier
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Sevier substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.