PacifiCorp-C4-005
199 MW hybrid in Millard, UT · In queue since April 2024 · Proposed COD December 2027
199 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PacifiCorp-C4-005 is a proposed 199 MW hybrid solar and battery project located in Millard County, Utah. The development project consists of 199 MW of solar generation, paired with battery storage. PacifiCorp, the utility and entity associated with the project, entered it into their interconnection queue on April 24, 2024. The proposed commercial operation date is December 31, 2027, with interconnection planned at the Black Rock substation.
The project is currently listed as active in the PacifiCorp interconnection queue. No interconnection agreement (IA) status is available. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
UT
County
Millard
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Black Rock substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-005