PacifiCorp-C4-012
197.8 MW hybrid in Iron, UT · In queue since April 2024 · Proposed COD May 2027
197.8 MW
Capacity
1
Components
Solar
2y 1m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-31
PacifiCorp-C4-012 is a proposed 197.8 MW hybrid solar and battery project located in Iron County, Utah. The development project consists of 197.8 MW of solar capacity. It is listed in the PacifiCorp interconnection queue as of April 30, 2024, with a proposed commercial operation date of May 31, 2027. The point of interconnection is the Sigurd Three Peaks transmission line.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Iron
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Sigurd Three Peaks transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.