Project PacifiCorp-C4-015 — Project Summary

Queue ID
PacifiCorp-C4-015
Capacity
1.6 MW
Technology
Solar
Status
active
Location
Multnomah, OR
Region
West
Developer
IA Status

PacifiCorp-C4-015

PacifiCorp-C4-015BetaActiveSolarPacifiCorpLBNL

1.6 MW generation in Multnomah, OR · In queue since May 2024 · Proposed COD September 2026

1.6 MW

Capacity

1

Components

Solar

2 years

In Queue

IA Status

COD target: 2026

Interconnection

Total Duration

2y 4m

Pre-Study0%
Queue EntryMay 6, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-01

About

PacifiCorp-C4-015 is a proposed solar generation project located in Multnomah County, Oregon, with a total capacity of 1.6 MW. The project consists of 1.6 MW of solar photovoltaic generation. It is listed in the PacifiCorp interconnection queue with an entry date of May 6, 2024, and a proposed commercial operation date of September 1, 2026.

The point of interconnection for PacifiCorp-C4-015 is Circuit 5P478 out of the Columbia substation. As of the latest data, the project is listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Multnomah

Grid Region

Mountain West

Market

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Circuit 5P478 out of Columbia substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PacifiCorp-C4-015