PacifiCorp-C4-022
500 MW storage in Salt Lake, UT · In queue since May 2024 · Proposed COD December 2029
500 MW
Capacity
1
Components
Battery
2 years
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
PacifiCorp-C4-022 is a proposed 500 MW battery storage project located in Salt Lake County, Utah. The project, developed by PacifiCorp, consists entirely of battery storage. It is currently active in the PacifiCorp interconnection queue, with an entry date of May 8, 2024, and a proposed commercial operation date of December 31, 2029. The point of interconnection is the Oquirrh substation.
The project is located in the Western region of the United States. As of the current data, there is no record of an interconnection agreement (IA) being reached, nor is there any indication of recent news coverage or a match to an existing operating plant in the EIA database.
Generated from interconnection queue and public data sources
State
UT
County
Salt Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Oquirrh substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.