PacifiCorp-C4-034
400 MW hybrid in Emery, UT · In queue since May 2024 · Proposed COD December 2030
400 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2030
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
PacifiCorp-C4-034 is a proposed 400 MW hybrid solar and battery project located in Emery County, Utah. The development project consists of 400 MW of solar generation. It is listed in the PacifiCorp interconnection queue as of May 14, 2024, with a proposed commercial operation date of December 31, 2030. The point of interconnection is the Emery Sigurd #1 transmission line.
The project is currently listed as active in the interconnection queue. No interconnection agreement (IA) status is available. The developer is PacifiCorp. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Emery Sigurd #1 transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.