PacifiCorp-C4-037
199 MW storage in Salt Lake, UT · In queue since May 2024 · Proposed COD December 2027
199 MW
Capacity
1
Components
Battery
2 years
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
PacifiCorp-C4-037 is a proposed 199 MW battery storage project located in Salt Lake County, Utah. The project, developed by PacifiCorp, consists entirely of battery storage. It is currently active in the PacifiCorp interconnection queue with an entry date of May 14, 2024, and a proposed commercial operation date of December 15, 2027. The point of interconnection is the Magna substation.
Generated from interconnection queue and public data sources
State
UT
County
Salt Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Magna substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-037