PacifiCorp-C4-042
330 MW hybrid in Carbon, WY · In queue since May 2024 · Proposed COD January 2029
330 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-01-12
PacifiCorp-C4-042 is a proposed 330 MW hybrid solar and battery project located in Carbon County, Wyoming. The development project consists of 330 MW of solar generation, coupled with battery storage. It is listed in the PacifiCorp interconnection queue as of May 15, 2024, with a proposed commercial operation date of January 12, 2029. The point of interconnection is the Platte substation.
The project is currently listed as active in the interconnection queue. There is no information available regarding an interconnection agreement or news coverage.
Generated from interconnection queue and public data sources
State
WY
County
Carbon
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Platte substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-042