PacifiCorp-C4-044
120 MW generation in Douglas, OR · In queue since May 2024 · Proposed COD December 2029
120 MW
Capacity
1
Components
Wind
2 years
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
PacifiCorp-C4-044 is a proposed 120 MW wind generation project located in Douglas County, Oregon. The project, developed by PacifiCorp, is actively listed in the PacifiCorp interconnection queue as of May 15, 2024. It is slated to connect to the Dixonville substation.
The proposed commercial operation date for the PacifiCorp-C4-044 project is December 1, 2029.
Generated from interconnection queue and public data sources
State
OR
County
Douglas
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Dixonville substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.