PacifiCorp-C4-048
250 MW storage in Salt Lake, UT · In queue since May 2024 · Proposed COD December 2027
250 MW
Capacity
1
Components
Battery
2 years
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-15
PacifiCorp-C4-048 is a proposed 250 MW battery storage project located in Salt Lake County, Utah. The project consists of a single 250 MW battery component. It is listed in the PacifiCorp interconnection queue as entry C4-048, with a queue entry date of May 15, 2024, and a proposed commercial operation date of December 15, 2027. The point of interconnection is the Copperhill substation.
The development project is currently listed as active in the interconnection queue. The developer is PacifiCorp. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
UT
County
Salt Lake
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Copperhill substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.