PacifiCorp-C4-050
199.9 MW storage in Sweetwater, WY · In queue since May 2024 · Proposed COD October 2028
199.9 MW
Capacity
1
Components
Battery
2 years
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-31
PacifiCorp-C4-050 is a proposed 199.9 MW battery storage project located in Sweetwater County, Wyoming. The development project, sponsored by PacifiCorp, consists entirely of battery storage. It is currently listed as active in the PacifiCorp interconnection queue, with an entry date of May 15, 2024, and a proposed commercial operation date of October 31, 2028. The point of interconnection is the Anticline substation.
The project is located in the Western region. As of the latest data, it does not have an executed Interconnection Agreement. The project has appeared in recent news coverage regarding PacifiCorp's grid modernization efforts.
Generated from interconnection queue and public data sources
State
WY
County
Sweetwater
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Anticline substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.