PacifiCorp-C4-052
199.9 MW hybrid in Tooele, UT · In queue since May 2024 · Proposed COD December 2028
199.9 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PacifiCorp-C4-052 is a proposed 199.9 MW hybrid solar and battery project located in Tooele County, Utah. The development project, sponsored by PacifiCorp, consists of 199.9 MW of solar generation capacity. It is currently active in the PacifiCorp interconnection queue (queue entry date: May 15, 2024) with a proposed commercial operation date of December 31, 2028. The point of interconnection is the Clover Limber transmission line.
The proposed project is located in the Western region of the United States. It is listed as a hybrid project type, combining solar and battery technologies. The project is in an active status within the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Tooele
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Clover Limber transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-052