PacifiCorp-C4-057
19.9 MW hybrid in Jefferson, OR · In queue since May 2024 · Proposed COD December 2028
19.9 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PacifiCorp-C4-057 is a proposed 19.9 MW hybrid solar and battery project located in Jefferson County, Oregon. The development project, sponsored by PacifiCorp, consists of 19.9 MW of solar capacity. It is currently active in the PacifiCorp interconnection queue, with an entry date of May 15, 2024, and a proposed commercial operation date of December 31, 2028. The point of interconnection is the Cove substation.
The project is located in the West region. No interconnection agreement (IA) status is available. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Cove substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-057