PacifiCorp-C4-065
199.9 MW storage in Emery, UT · In queue since May 2024 · Proposed COD October 2028
199.9 MW
Capacity
1
Components
Battery
2 years
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-31
PacifiCorp-C4-065 is a proposed 199.9 MW battery storage project located in Emery County, Utah. The development project, sponsored by PacifiCorp, entered the PacifiCorp interconnection queue on May 15, 2024. The proposed commercial operation date is October 31, 2028.
The project consists of a single 199.9 MW battery component. Interconnection will occur at the Emery substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Emery substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-065