Project PacifiCorp-C4-066 — Project Summary

Queue ID
PacifiCorp-C4-066
Capacity
62 MW
Technology
Gas
Status
active
Location
Utah, UT
Region
West
Developer
PacifiCorp
IA Status

PacifiCorp-C4-066

PacifiCorp-C4-066BetaActiveGasPacifiCorpLBNL

62 MW generation in Utah, UT · In queue since May 2024 · Proposed COD January 2026

62 MW

Capacity

1

Components

Gas

2 years

In Queue

IA Status

COD target: 2026

Interconnection

Total Duration

1y 8m

Schedule

4 months past proposed COD

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-01

About

PacifiCorp-C4-066 is a proposed 62 MW gas-fired generation project located in Utah County, Utah. The project, developed by PacifiCorp, entered the PacifiCorp interconnection queue on May 15, 2024, with a proposed commercial operation date of January 1, 2026. The point of interconnection is the Dynamo substation.

The project consists of 62 MW of gas-fired generation capacity. The project is currently listed as active in the interconnection queue.

Generated from interconnection queue and public data sources

Project Details

State

UT

County

Utah

Grid Region

Mountain West

Market

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Dynamo substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PacifiCorp-C4-066