PacifiCorp-C4-067
73 MW generation in Utah, UT · In queue since May 2024 · Proposed COD January 2026
73 MW
Capacity
1
Components
Gas
2 years
In Queue
—
IA Status
COD target: 2026
Total Duration
1y 8m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
PacifiCorp-C4-067 is a proposed 73 MW gas-fired generation project located in Utah County, Utah. The project, being developed by PacifiCorp, entered the PacifiCorp interconnection queue on May 15, 2024, with a proposed commercial operation date of January 1, 2026. The point of interconnection is the Steel Mill substation.
The proposed project consists of 73 MW of gas-fired generation capacity. It is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
UT
County
Utah
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Steel Mill substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-067