Project PacifiCorp-C4-086 — Project Summary

Queue ID
PacifiCorp-C4-086
Capacity
450 MW
Technology
Solar
Status
active
Location
Emery, UT
Region
West
Developer
IA Status

PacifiCorp-C4-086

PacifiCorp-C4-086BetaActiveSolarPacifiCorpLBNL

450 MW generation in Emery, UT · In queue since May 2024 · Proposed COD May 2029

450 MW

Capacity

1

Components

Solar

2 years

In Queue

IA Status

COD target: 2029

Interconnection

Total Duration

5 years

Pre-Study0%
Queue EntryMay 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-05-31

About

PacifiCorp-C4-086 is a proposed 450 MW solar generation project located in Emery County, Utah. The project is listed in the PacifiCorp interconnection queue with an entry date of May 15, 2024, and a proposed commercial operation date of May 31, 2029. The point of interconnection is the Camp Williams - Emery transmission line.

The development project is currently listed as active in the interconnection queue. No interconnection agreement status is available. The project has appeared in recent news coverage regarding PacifiCorp's queue.

Generated from interconnection queue and public data sources

Project Details

State

UT

County

Emery

Grid Region

Mountain West

Market

Developer

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Camp Williams - Emery transmission line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.