PacifiCorp-C4-088
199 MW hybrid in Utah, UT · In queue since May 2024 · Proposed COD December 2027
199 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PacifiCorp-C4-088 is a proposed 199 MW hybrid solar and battery project located in Utah County, Utah. The project, developed by PacifiCorp, consists of 199 MW of solar capacity. It is currently listed as active in the PacifiCorp interconnection queue, with an entry date of May 15, 2024, and a proposed commercial operation date of December 31, 2027. The point of interconnection is the Fairfield substation.
The proposed project is located in the western region of the United States. It is a hybrid project, combining solar and battery technologies.
Generated from interconnection queue and public data sources
State
UT
County
Utah
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Fairfield substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-088