PacifiCorp-C4-090
199 MW generation in Bonneville, ID · In queue since May 2024 · Proposed COD December 2028
199 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PacifiCorp-C4-090 is a proposed solar generation project located in Bonneville County, Idaho, with a total capacity of 199 MW. The project consists of 199 MW of solar photovoltaic generation. It is listed in the PacifiCorp interconnection queue as entry C4-090, with a queue entry date of May 15, 2024, and a proposed commercial operation date of December 31, 2028. The point of interconnection is the Goshen - Jefferson transmission line.
The project is currently listed as active in the interconnection queue. There is recent news coverage of the project.
Generated from interconnection queue and public data sources
State
ID
County
Bonneville
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Goshen - Jefferson transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.