PacifiCorp-C4-092
1,280 MW hybrid in Harney, OR · In queue since May 2024 · Proposed COD May 2031
1,280 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2031
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-01
PacifiCorp-C4-092 is a proposed 1280 MW hybrid solar and battery project located in Harney County, Oregon. The development project consists of 1280 MW of solar generation, coupled with battery storage. It is listed in the PacifiCorp interconnection queue as of May 15, 2024, with a proposed commercial operation date of May 1, 2031.
The point of interconnection for the project is the Burns Summer Lake transmission line. The project is currently listed as active in the interconnection queue. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
OR
County
Harney
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Burns Summer Lake transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.