PacifiCorp-C4-093
1,280 MW hybrid in Klamath, OR · In queue since May 2024 · Proposed COD May 2031
1,280 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2031
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-01
PacifiCorp-C4-093 is a proposed 1280 MW hybrid solar and battery project located in Klamath County, Oregon. The development project consists of 1280 MW of solar capacity. It is listed in the PacifiCorp interconnection queue as of May 15, 2024, with a proposed commercial operation date of May 1, 2031. The point of interconnection is the Corral - Snow Goose transmission line.
The project is currently listed as active in the interconnection queue. There is recent news coverage of the project.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Corral - Snow Goose transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.