PacifiCorp-C4-094
8 MW generation in Bighorn, MT · In queue since May 2024
8 MW
Capacity
1
Components
Hydro
2 years
In Queue
—
IA Status
Total Duration
2 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
PacifiCorp-C4-094 is a proposed 8 MW hydroelectric generation project located in Bighorn County, Montana. The project, developed by PacifiCorp, is slated to interconnect at the Yellowtail substation. It entered the PacifiCorp interconnection queue on May 15, 2024.
The project is currently listed as active in the interconnection queue. No proposed commercial operation date or interconnection agreement (IA) status is available.
Generated from interconnection queue and public data sources
State
MT
County
Bighorn
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Yellowtail substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.