PacifiCorp-C4-106
300 MW generation in Bingham, ID · In queue since May 2024 · Proposed COD June 2030
300 MW
Capacity
1
Components
Wind
2 years
In Queue
—
IA Status
COD target: 2030
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
PacifiCorp-C4-106 is a proposed 300 MW wind generation project located in Bingham County, Idaho. The project is sponsored by PacifiCorp and consists of 300 MW of wind generation capacity. It is listed in the PacifiCorp interconnection queue as entry C4-106, with a queue entry date of May 15, 2024, and a proposed commercial operation date of June 1, 2030. The point of interconnection is the Goshen substation.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
ID
County
Bingham
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Goshen substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PacifiCorp-C4-106