24.9 MW hybrid in Modoc, CA · In queue since May 2024 · Proposed COD December 2026
24.9 MW
Capacity
1
Components
Solar
2 years
In Queue
—
IA Status
COD target: 2026
Total Duration
2y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-29
PacifiCorp-C4-112 is a proposed 24.9 MW hybrid solar and battery energy project located in Modoc County, California. The project consists of 24.9 MW of solar generation. It is listed in the PacifiCorp interconnection queue as of May 15, 2024, with a proposed commercial operation date of December 29, 2026. The point of interconnection is the Alturas - Mile Hi transmission line.
The project is currently listed as active in the interconnection queue. Recent news coverage indicates interest in renewable energy projects in the West region.
Generated from interconnection queue and public data sources
State
CA
County
Modoc
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Alturas - Mile Hi transmission line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.